Project Spotlights

Synchronous Condenser Project at a 1,400 MW Wind Base: ETENZ Enclosures in Place

E
ETENZ•Editorial Team

At the 500 kV collector substation of a 1,400 MW wind project in Abag Banner, Inner Mongolia, ETENZ built the enclosures for NR Electric's 2 × 50 Mvar synchronous condenser project: two condenser buildings and two electrical E-⁠Houses. The container enclosures of Sieyuan Electric's grid-forming BESS at the same substation also came from ETENZ. All are in place on site, and equipment installation is under way.

Rows of Sieyuan grid-forming BESS units at the Abag Banner 500 kV substation, wind turbines and a power line behind

The 500 kV collector substation in Abag Banner, Xilingol League, carries the output of a 1,400 MW wind project in Inner Mongolia to the grid. Its 2 × 50 Mvar synchronous condensers and its grid-forming battery energy storage system (BESS) both sit in enclosures built by ETENZ: four condenser enclosures for NR Electric's synchronous condenser project, and the container enclosures of Sieyuan Electric's grid-forming BESS. The enclosures are in place on site, and equipment installation is under way.

Synchronous condensers in two 9 m high buildings

Each 50 Mvar synchronous condenser sits in its own condenser building, 45.2 × 12.4 × 9 m, together with its lube oil and water cooling units; the condenser dry coolers stand outside, with their pipes entering through the wall. Two electrical E-⁠Houses, 44.2 × 9.2 × 3.75 m, hold the switchgear and control panels.

End of a synchronous condenser building with three tiers of wall panels and dry cooler pipes, wind turbine behind
Each 50 Mvar synchronous condenser sits in a 45.2 × 12.4 × 9 m condenser building

ETENZ manufactured the four structures and fitted their auxiliary systems: wall-mounted industrial air conditioners, filter fans, lighting and emergency lighting, power distribution and earthing, fire extinguishers and anti-static flooring. NR Electric and the equipment makers supplied the condensers, excitation and control equipment. The project is described in the case study Abag Banner synchronous condenser buildings and electrical E-⁠Houses.

Grid-forming BESS containers from the same factory

At the same substation, the container enclosures of Sieyuan Electric's grid-forming BESS were also manufactured by ETENZ. Grid-forming storage actively supports grid voltage and frequency and, together with the synchronous condensers, strengthens the system that carries large-scale wind power to the grid. ETENZ builds BESS enclosures in volume for storage system makers including Sieyuan Electric, NR Electric and Sungrow.

Front of a Sieyuan grid-forming BESS unit: storage containers at both ends, transformer and HV rooms in the middle
Grid-forming BESS at the same substation; ETENZ built the storage container enclosures

Built in the factory, set in place on site

The condenser enclosures and BESS containers were built in the factory and set on their foundations at site, so enclosure production ran in parallel with the substation's civil works. Since 2023, ETENZ has supplied prefabricated enclosures for more than 20 of NR Electric's synchronous condenser projects.

Tags

synchronous condenser projectgrid forming BESSsynchronous condenser renewable energygrid forming battery storagesynchronous condenser wind power

Share Article

Thank you for sharing ETENZ content

Have a project in mind?

Message us on WhatsApp or send an inquiry. We reply within 24 hours on working days.