ETENZ E-House Modules Support the ASE Solar Plant’s 69 kV Substation
E
ETENZ•Editorial Team
ETENZ built the prefabricated E-House modules for the ASE solar power project’s 69 kV substation, using factory-based manufacturing and modular integration to improve delivery speed and project reliability.
ETENZ E-House modules are supporting the construction of the ASE solar power project. As clean energy projects continue to grow, prefabricated substations have become an important technical option because they can improve efficiency and support faster deployment. ETENZ recently completed a representative project: manufacturing the prefabricated E-House modules for the ASE solar power plant’s 69 kV substation.
Equipment assembly and integration inside the prefabricated electrical enclosure at the factory
The ASE solar power plant serves an energy market with rapidly growing demand, and its power export system depends on this newly built substation. ETENZ built the substation’s equipment rooms as prefabricated E-House modules, moving most of that construction work into the factory. This method improved construction efficiency and provided stronger control over engineering quality. The E-House has two levels. The first level houses primary equipment and was built by joining eight 40-foot container modules. The second level contains secondary equipment and uses six container modules of the same specification. This modular construction method makes assembly and transport more convenient and reliable.
Prefabricated substation module craned into position on site
Inside the ETENZ factory, the E-House modules were built from the ground up and completed in 90 days, covering enclosure manufacturing, internal wiring, installation and fastening of primary and secondary equipment, and GIS fixing and installation. This factory-based production model helped standardize and systematize the manufacturing process while significantly shortening the overall project schedule.
GIS switchgear arranged inside the substation enclosure
Once the E-House modules arrived on site, lifting and installation were completed in just 15 days, a speed that is difficult to achieve with traditional substation construction. This rapid deployment capability saved valuable time for the customer and helped reduce construction cost.
First-level enclosure completed during construction
The successful delivery of this project demonstrates ETENZ’s capability in building E-Houses for prefabricated substations and provides practical experience for future projects of the same type. With advantages in efficiency, environmental performance and cost control, prefabricated substations are expected to see broader use in global energy infrastructure.