It follows the maintenance regime and the oil-testing requirement. In the sealed unit the oil does not meet air, no topping-up or filtering is needed in service, and there is no conservator or breather to look after, which suits lightly attended and widely scattered sites. The conventional unit keeps the conservator, the oil level is visible and oil samples are easy to draw, which is common on network projects with a scheduled oil-testing regime. Note that the overall dimensions differ — close to 260 mm in length at 630 kVA — so set out the foundation for whichever is chosen.

Oil-Immersed Distribution Transformer
For distribution contractors, panel builders and industrial project owners: the ETENZ oil-immersed distribution transformer covers 30–2500 kVA at 10 kV and 20 kV, in loss generations S11 to S22 and in fully sealed or conventional tank construction, supplied as a single unit or delivered with a prefabricated power module or a package substation.
Key Metrics
Product Features
Fully sealed tank
The corrugated tank absorbs the thermal expansion and contraction of the oil through its own deformation, the oil never meets air, and no topping-up or filtering is needed in service — there is no conservator and no breather to look after. A conventional non-sealed construction is available at the same capacity, and the two have different overall dimensions: at 630 kVA, 1370×890×1470 against 1630×890×1570 mm. Be clear which one the layout drawing is for.
Fully sealed tank
The corrugated tank absorbs the thermal expansion and contraction of the oil through its own deformation, the oil never meets air, and no topping-up or filtering is needed in service — there is no conservator and no breather to look after. A conventional non-sealed construction is available at the same capacity, and the two have different overall dimensions: at 630 kVA, 1370×890×1470 against 1630×890×1570 mm. Be clear which one the layout drawing is for.
Fully sealed tank
The corrugated tank absorbs the thermal expansion and contraction of the oil through its own deformation, the oil never meets air, and no topping-up or filtering is needed in service — there is no conservator and no breather to look after. A conventional non-sealed construction is available at the same capacity, and the two have different overall dimensions: at 630 kVA, 1370×890×1470 against 1630×890×1570 mm. Be clear which one the layout drawing is for.
Two-slope ladder
From S11 to S13 only no-load loss moves, from 810 W to 570 W at 630 kVA, while load loss stays at 6200 W in both. At S20 and S22 both fall together: no-load 510 W and 460 W, load loss 4960 W and 4460 W. Carrying the S13 arithmetic over to S20 understates the saving.
Outdoor as standard
The lower ambient limit is −25 °C, and the unit can be installed in the open on a pole, on a platform or inside a package substation, with no dedicated indoor transformer room. Above 1000 m, outside the normal temperature range or in a corrosive environment, the special service conditions are settled separately.
Three vector groups
Dyn11, Yzn11 and Yyn0 are available. At 500 kVA and below, load loss varies with the vector group; from 630 kVA up the parameter table no longer separates them. Neutral earthing arrangement and unbalanced-load capability are settled against the system requirements.
Two tapping ranges
Two off-circuit ranges, ±5% and ±2×2.5%. The first has two tap positions and a coarse step, the second four positions and a finer step. Which one suits depends on how far the voltage swings at the end of the line and on the regulating accuracy that is acceptable; the switching procedure is the same for both.
Product Details

The leading S is three-phase oil-immersed, the digits that follow are the performance-level code, and M means the fully sealed construction — its absence means the conventional one. Rated capacity and rated high voltage follow the code, written as "-capacity/voltage". S13-M-630/10 therefore reads: three-phase oil-immersed, performance level 13, fully sealed, 630 kVA, 10 kV. On-load tap-changing versions add a Z after the leading letter, and a wound-core construction uses R in place of M; altitude, seismic and anti-corrosion service conditions carry their own suffix codes.

The fully sealed construction absorbs the change in oil volume through the elastic deformation of the corrugated tank wall. No air layer is left above the oil surface, the oil meets neither oxygen nor moisture, and in service there is no topping-up and no filtering — nor a conservator and a dehydrating breather to inspect periodically. The conventional construction keeps the conservator and the breathing system. It takes a little more maintenance, but the oil level is visible and oil samples are easy to draw, which keeps it common on network projects with a scheduled oil-testing regime. The two do not share one set of overall dimensions. At 630 kVA the sealed unit is 1370×890×1470 mm and the conventional one 1630×890×1570 mm — close to 260 mm apart in length, with the same 660×660 mm wheel gauge. Set out the foundation and the fence for whichever is chosen; mixing the two sets of dimensions is what fails to line up on site. Corrugated or panel radiating surfaces are welded directly to the tank wall, and natural circulation of the oil carries heat from the windings and the core to the wall and out into the air, with no fans and no oil pumps. Radiating surface grows with capacity, and that is the main reason the overall dimensions grow with it — 630 kVA weighs 1860 kg in total and 2500 kVA 5470 kg, with the wheel gauge widening from 660×660 mm to 1070×1070 mm. Plan transport and lifting on the actual weight of the capacity chosen rather than extrapolating in proportion.
From performance level S11 to S13 only the no-load loss column moves: 810 W to 570 W at 630 kVA, while load loss stays at 6200 W in both generations, and no-load current, impedance and dimensions do not change either. Every bit of the saving on this stretch comes from no-load, independently of the load factor. From S20 the slope changes. At 630 kVA no-load falls to 510 W and load loss to 4960 W; S22 gives 460 W and 4460 W. Both falling together means heavily loaded installations gain as well, and the payback arithmetic differs from the earlier stretch. So establish which stretch applies before estimating the saving: carrying S11-to-S13 experience over to S20 drops the whole load-side share of the gain.
Where an oil-immersed transformer goes into a package substation or a prefabricated power module, an oil pit or an oil-retention arrangement is needed inside, sized on the oil volume of the transformer. That is the main layout difference against a dry-type unit. Where the transformer is delivered with the module, ETENZ settles oil pit volume, ventilation opening area, clear space for the cooling air path, maintenance aisle width and lifting hole positions together at the module layout drawing stage; fire separation between the transformer room and the HV and LV rooms follows the code of the project location. Only the connection and a re-check before oil filling remain on site.
Delivery Scope Options
Single Unit or Complete Package Supply
Scope 1Single Unit or Complete Package Supply
Transformers are supplied as single units against the order schedule, or as a complete package together with the protective enclosure, the temperature controller and the cooling fans. The active part is wound, assembled and routine-tested at the works and shipped as a complete unit; the assembly interface for the accessories follows the transport conditions. Where the transformer is to arrive together with a prefabricated power module, the E-House line takes on the enclosure, the internal arrangement and the foundation fixing, and the transformer is delivered as equipment housed within it.
Scope Includes:
Single Unit or Complete Package Supply
Scope 1Single Unit or Complete Package Supply
Transformers are supplied as single units against the order schedule, or as a complete package together with the protective enclosure, the temperature controller and the cooling fans. The active part is wound, assembled and routine-tested at the works and shipped as a complete unit; the assembly interface for the accessories follows the transport conditions. Where the transformer is to arrive together with a prefabricated power module, the E-House line takes on the enclosure, the internal arrangement and the foundation fixing, and the transformer is delivered as equipment housed within it.
Scope Includes:
Technical Specifications
| Parameter | Specification |
|---|---|
| Product form | Three-phase two-winding oil-immersed distribution transformer with off-circuit tap changing |
| Rated capacity | 30–2500 kVA |
| Rated high voltage | 10 kV (6, 6.3, 10.5, 11 kV); a separate table covers the 20 kV class |
| Rated low voltage | 0.4 kV |
| Off-circuit tapping range | ±5% or ±2×2.5% |
| Vector group | Dyn11, Yzn11 or Yyn0 |
| Short-circuit impedance | 4.0% (≤500 kVA); 4.5% (630–1600 kVA); 5.0% (2000–2500 kVA, S20/S22) |
| No-load loss (630 kVA) | S11 810 W; S13 570 W; S20 510 W; S22 460 W |
| Load loss (630 kVA) | 6200 W for both S11 and S13; S20 4960 W; S22 4460 W |
| No-load current (630 kVA) | S13 1.1%; S20 0.6%; S22 0.6% |
| Vector group effect on load loss | Separated for Dyn11/Yzn11 and Yyn0 at 500 kVA and below; not separated from 630 kVA up |
| Tank construction | Fully sealed or conventional |
| Overall dimensions (630 kVA, sealed) | 1370×890×1470 mm |
| Overall dimensions (630 kVA, conventional) | 1630×890×1570 mm |
| Total weight (630 kVA) | 1860 kg (core and windings 1240 kg, oil 280 kg) |
| Wheel gauge (longitudinal × transverse) | 400×400 to 1070×1070 mm, set by capacity |
| Cooling | ONAN oil-immersed natural cooling |
| Installation | Outdoor on ground, on a platform, or inside a package substation |
| Service conditions | Outdoor; maximum +40 °C, minimum −25 °C, hottest month average +30 °C, altitude not above 1000 m |
| Special service conditions | High altitude, seismic and anti-corrosion versions carry their own suffix codes |
Product FAQs
First establish which stretch applies. S11 to S13 lowers only no-load loss (810 W to 570 W at 630 kVA) while load loss stays at 6200 W, so the saving is independent of load factor and follows directly from the annual hours. From S20 no-load and load loss fall together (510 W and 4960 W; S22 gives 460 W and 4460 W), so heavily loaded sites gain a further share. Carrying earlier experience over to S20 understates the saving. Send the annual running hours, the average load factor and the tariff and the generation that pays can be calculated.
It follows the installation position and the fire-protection conditions. The oil-immersed unit can be arranged outdoors, has a lower ambient limit of −25 °C, and at the same capacity has lower no-load loss and usually a lower unit price; the price is an oil pit or oil-retention arrangement and the fire-protection requirements that come with oil. The dry-type unit is an indoor machine, can be placed directly at the load centre and needs no oil pit, which favours damp environments and underground substations, but its low-temperature limit is only −5 °C. Inside a prefabricated power module no oil pit is provided, which is why the great majority there are dry-type.
The number of tap positions and the step size. ±5% gives two positions in 5% steps, ±2×2.5% gives four positions in 2.5% steps. The first suits a line end whose voltage swings widely but where fine accuracy is not required; the second suits finer regulation. Both are off-circuit: the transformer has to be de-energised to change taps, and they cannot be switched on load.
From the unbalanced-load capability required on the low-voltage side and the neutral earthing requirement. All three are available; at 500 kVA and below the parameter table separates load loss by vector group, and from 630 kVA up it no longer does. On a specific project the phase relationship with the equipment upstream and downstream, the protection configuration and the conditions for parallel operation all have to be checked alongside, and the choice is confirmed before ordering.
Yes. Where it travels with the module, the prefabricated power module line takes on the enclosure, the internal arrangement and the foundation fixing, and the transformer leaves the works as equipment inside it. What matters for an oil-immersed unit is the oil pit or oil-retention arrangement — sized on the oil volume and settled in one pass at the layout drawing stage together with ventilation opening area, clear cooling space, maintenance aisle width and fire separation. Supply of the transformer on its own is equally possible.
On the actual total weight of the capacity chosen, not on a proportional extrapolation. At 630 kVA the total is 1860 kg (core and windings 1240 kg, oil 280 kg) and at 2500 kVA it is 5470 kg, with the wheel gauge widening from 660×660 mm to 1070×1070 mm. Radiating surface grows with capacity, so weight does not grow in proportion to it. Whether the oil is drained for long-distance transport is settled separately.
Related Solutions
Prefabricated E-House Project Delivery Solution
ETENZ delivers configurable prefabricated E-House projects for electrical equipment integration, covering enclosure manufacturing, layout, wiring paths, factory checks, interface coordination, and OEM/ODM cooperation.





Related Products

Integrated E-House

MV Switchgear E-House

Containerized MV Switchgear E-House

Amorphous Alloy Oil-Immersed Transformer

Triangular Wound Core Oil-Immersed Transformer








